Line Extension Services
Company-Constructed Line Extensions and Relocations
Underground Construction
Effective Sept. 21, 2000
| |
Single-Phase Service |
Three-Phase Service |
| Application Fee (Non-Refundable) |
$450 |
$505 |
| Underground Conduit per ft. 3-inch diameter |
$3.12 |
$3.12 |
| 5-inch diameter |
$5.71 |
$5.71 |
| Jacketed Primary Cable per foot |
$2.47 |
$7.39 |
| Riser - each |
$1,390 |
$2,460 |
| Underground Feed - In |
$135 |
$400 |
| - Out |
$245 |
$735 |
| Fault Indicator |
$110 |
$330 |
| Open Loop |
$150 |
$455 |
| Insulating Receptacle |
$50 |
$160 |
| Terminating Cabinet |
$1,575 |
$1,940 |
| Feed Through Junction |
$180 |
$535 |
| Loadbreak Elbow |
$135 |
$400 |
| Junction - 3-way |
$180 |
$535 |
| - 4-way |
$190 |
$580 |
| Pad Mount Foundation |
$765 |
$2,200 |
| Service Cable |
Estimated |
Estimated |
| Service Credit, if applicable |
$(210) |
$(210) |
| Each Right-of-Way in Excess of One |
$220 |
$220 |
Padmount Transformer
Cost Differential All Units $25/kva
Up to 300 kva $15/kva
Over 300 kva Actual
|
| Special Construction Charges |
Actual |
Actual |
| Act 250 Permit Charges, when required |
Actual |
Actual |
| Other Special Permit Charges |
Actual |
Actual |
| Relocation: Salvage or Removal |
Actual |
Actual |
Tax Assessment Applicable to the Sum
of the Above Charges |
34.8% |
34.8% |
|