Line Extension Services
Company-Constructed Line Extensions and Relocations
Three-Phase Overhead
Effective Sept. 21, 2000
| |
Joint w/Telephone |
Not Joint w/Telephone |
| Application Fee (Non-Refundable) |
$580 |
$580 |
| |
|
|
| Primary Line: |
|
|
| Last Pole |
$1410 |
$1820 |
| Each Additional Pole |
$680 |
$980 |
| Conductor/Foot |
$6.10 |
$6.10 |
| |
|
|
| Secondary Line: |
|
|
| Last Pole |
$810 |
$1190 |
| Each Additional Pole |
$280 |
$550 |
| Conductor/Foot |
$2.80 |
$2.80 |
| Each Guy/Anchor/Brace
Assembly, when required |
$130 |
$130 |
Additional Charge for Each Pole Set
in Rock Ledge |
$410 |
$410 |
| Service Drop Rating 175 Ampere |
$3.20/ft |
$3.20/ft |
| 270 Ampere |
$7.10/ft |
$7.10/ft |
| 330 Ampere |
$8.60/ft |
$8.60/ft |
| Service Drop Credit, if applicable |
$(210) |
$(210) |
| Each Right-of-Way in Excess of One |
$110 |
$220 |
| Special Construction Charges |
Actual |
Actual |
| Act 250 Permit Charges, when required |
Actual |
Actual |
| Other Special Permit Charges |
Actual |
Actual |
| Relocation: Salvage or Removal |
Actual |
Actual |
Tax Assessment Applicable to the Sum
of the Above Charges |
34.8% |
34.8% |
|