Home > Programs and Services > Line Extension Services > Three-Phase Overhead Extensions
Line Extension Services
Company-Constructed Line Extensions and Relocations
Three-Phase Overhead Effective Oct. 8, 2008
|
|
Joint w/Telephone
|
Not Joint w/Telephone
|
|
Application Fee (Non-Refundable) |
$580
|
$580
|
|
|
|
|
|
Primary Line: |
|
|
|
Last Pole |
$1410
|
$1820
|
|
Each Additional Pole |
$680
|
$980
|
|
Conductor/Foot |
$6.10
|
$6.10
|
|
|
|
|
|
Secondary Line: |
|
|
|
Last Pole |
$810
|
$1190
|
|
Each Additional Pole |
$280
|
$550
|
|
Conductor/Foot |
$2.80
|
$2.80
|
|
Each Guy/Anchor/Brace Assembly, when required |
$130
|
$130
|
Additional Charge for Each Pole Set
in Rock Ledge |
$410
|
$410
|
|
Service Drop Rating 175 Ampere |
$3.20/ft
|
$3.20/ft
|
|
270 Ampere |
$7.10/ft
|
$7.10/ft
|
|
330 Ampere |
$8.60/ft
|
$8.60/ft
|
|
Service Drop Credit, if applicable |
$(210)
|
$(210)
|
|
Each Right-of-Way in Excess of One |
$110
|
$220
|
|
Special Construction Charges |
Actual
|
Actual
|
|
Act 250 Permit Charges, when required |
Actual
|
Actual
|
|
Other Special Permit Charges |
Actual
|
Actual
|
|
Relocation: Salvage or Removal |
Actual
|
Actual
|
|
Utility tax liability arising under Federal Tax Reform Act of 1986 |
34.8%
|
34.8%
|
|