Line Extension Services

Company-Constructed Line Extensions and Relocations
Single-Phase Overhead Effective Sept. 21, 2000

 
Joint w/Telephone
Not Joint w/Telephone
Application Fee (Non-Refundable)
$345
$345
 
Primary Line:
Last Pole
$583
$980
Each Additional Pole
$323
$610
Conductor/Foot
$1.80
$1.80
 
Secondary Line:
Last Pole
$490
$830
Each Additional Pole 
$230
$460
Conductor/Foot
$2.20
$2.20
Each Guy/Anchor/Brace Assembly, when required
$120
$120
Additional Charge for Each Pole Set
in Rock Ledge
$410
$410
Service Drop Rating 100 Ampere
$2.10/ft
$2.10/ft
200 Ampere
$2.90/ft
 $2.90/ft
300 Ampere
 $6.40/ft
$6.40/ft
400 Ampere
$7.30/ft
$7.30/ft
Service Drop Credit, if applicable
$(210)
$(210)
Each Right of Way in Excess of One
$110
$220
Special Construction Charges
Actual
Actual
Act 250 Permit Charges when required
Actual
Actual
Other Special Permit Charges
Actual
Actual
Relocation: Salvage or Removal
Actual
Actual
Tax Assessment Applicable to the Sum
of the Above Charges 
34.8%
34.8%

 