Home > Programs and Services > Line Extension Services > Single-Phase Overhead Extensions
Line Extension Services
Company-Constructed Line Extensions and Relocations
Single-Phase Overhead Effective Oct. 8, 2008
|
|
Joint w/Telephone
|
Not Joint w/Telephone
|
|
Application Fee (Non-Refundable) |
$345
|
$345
|
|
|
|
|
|
Primary Line: |
|
|
|
Last Pole |
$583
|
$980
|
|
Each Additional Pole |
$323
|
$610
|
|
Conductor/Foot |
$1.80
|
$1.80
|
|
|
|
|
|
Secondary Line: |
|
|
|
Last Pole |
$490
|
$830
|
|
Each Additional Pole |
$230
|
$460
|
|
Conductor/Foot |
$2.20
|
$2.20
|
|
Each Guy/Anchor/Brace Assembly, when required |
$120
|
$120
|
Additional Charge for Each Pole Set
in Rock Ledge |
$410
|
$410
|
|
Service Drop Rating 100 Ampere |
$2.10/ft
|
$2.10/ft
|
|
200 Ampere |
$2.90/ft
|
$2.90/ft
|
|
300 Ampere |
$6.40/ft
|
$6.40/ft
|
|
400 Ampere |
$7.30/ft
|
$7.30/ft
|
|
Service Drop Credit, if applicable |
$(210)
|
$(210)
|
|
Each Right of Way in Excess of One |
$110
|
$220
|
|
Special Construction Charges |
Actual
|
Actual
|
|
Act 250 Permit Charges when required |
Actual
|
Actual
|
|
Other Special Permit Charges |
Actual
|
Actual
|
|
Relocation: Salvage or Removal |
Actual
|
Actual
|
Utility tax liability arising under Federal Tax Reform Act of 1986
|
34.8%
|
34.8%
|
|