Line Extension Services

Customer-Constructed Line Extensions and Relocations
Overhead or Underground Effective Oct. 8, 2008

The following charges shall be applicable to each customer constructed line extension and relocation:

 
Single-Phase Service
Three-Phase Service
Application Fee (non-refundable)
$345
$365
Engineering, Survey and Design - Overhead
$100/pole
Actual
                                                    - Underground
Actual
Actual
Administrative Charge
4% of project cost
4% of job cost
Inspection Underground
Actual
Actual
Inspection Overhead per application
$50/pole
$50/pole
Underground Cable Termination
using customer supplied materials
              Riser
$680
$1125
             Load Break Elbow
$95
$290
Each Right-of-Way in Excess of One
$220
$220
Special Construction Charges
Actual
Actual
Act 250 Permit Charges, if required
Actual
Actual
Other Special Permit Charges
Actual
Actual
Relocation: Salvage or Removal
Actual
Actual
Service Drop Credit, if applicable
$(210)
$(210)
Customer Owner Primary:
Pole-mounted metering
$2,700
Actual
Pad-mounted metering
$6,700
Actual
Inspection
$60/hour
$60/hour

An adjustment for Utility tax liability arising under Federal Tax Reform Act of 1986 equal to 34.8% of the reasonable cost or value of each installation for which the Company accepts ownership will be applicable. The applicant shall provide proof of the cost of such facilities in such detail as the Company may reasonably request.

 